Bench test

The bench test makes sure that system installation is efficient and machine downtime is minimized.
Complete the bench test before system installation. If possible, take time to get replacements for components that are missing or have damage.
  1. Open the hardware kit boxes and use the packing lists to make sure that all system items are present and have no damage.
  2. Find the system configuration for your machine installation.
  3. Use the applicable system diagram and the cables from the kit to connect the components.
    ADDITIONAL INFORMATION: The following cables are necessary for the bench test, dependent on the MC-X controller used.
    Part NumberDescription
    1033631-02MC-X3 Breakout CBL GX-55 (MC-X1 and MC-X3)
    1048078-01MC-X1 to MC-X3 Harness Adapter (MC-X1)
    1017799-01MC-X1 Programming Cable (MC-X1)
  4. Make sure that each component has the latest applicable software/firmware and update each as necessary during the bench test.
    ADDITIONAL INFORMATION:
    This saves time during the installation because it will not be necessary to update components in the field. It gives confirmation that all components operate before installation.
    Caution:
    Connect to power only after all components are connected.
  5. Connect to power after you connect all components.
    ADDITIONAL INFORMATION:
    A 12 VDC battery is a sufficient power source.
    If an SC024 controller is part of the test, you must connect it to switched power.

myTopcon NOW! support

Take your Topcon experience to the next level with myTopcon NOW! This platform is a self-service tool for your desktop or mobile device. 

Product manuals
paper icon
Communications
phone icon
E-learning
hat icon
Quick start guides
support icon
Firmware & software updates
cloud icon
Troubleshooting
webinars icon